Waterbury Dam Still Needs More Repair Work Done; Awaits Fed Funds

The Waterbury Dam, which was built in 1938 and repaired numerous times, most recently in 2007, needs additional work, which may be completed if it receives federal funding.

The Waterbury Dam, which was built in 1938 and repaired numerous times, most recently in 2007, needs additional work, which may be completed if it receives federal funding.

The Waterbury Dam, which was built in 1938 and repaired numerous times, most recently in 2007, needs additional work, which may be completed if it receives federal funding.

Sen. Patrick Leahy said money for repairs is included in a $20 million appropriation included in the Senate’s Energy and Water Appropriations bill, which must be approved by the full Congress and signed by the president.

Benjamin Green, an engineer for Vermont’s Dam Safety program, said a Risk Assessment must first be performed, followed by a Dam Safety Modification Report prior to final design and construction.

“The Risk Assessment, Modification Report and Design will likely take several years so it could be four to five years or more before construction begins,” he said.

Green noted that the last significant repair of the dam was in the early 2000s and was related to seepage. A partial secant cut-off wall was installed but couldn’t be completed due to technical issues.

“Six dewatering wells were also installed to pump leakage water out of the dam, he said. “During this project, and during regular test operations of the flood gates at the principal spillway, one of the gates jammed. This required temporary repairs to the gates and prompted a structural analysis of the gates, which deemed them unable to safely maintain a full flood pool. The objective of the upcoming spillway repair project is to permanently address the issues with the flood gates and spillway through repair or replacement.”

The job will be completed through a partnership between the state of Vermont, the dam owner, and the Army Corps of Engineers, who originally designed and oversaw construction of the dam and continues to provide the state with technical and funding assistance.

“We would do the Risk Assessments and other items to evaluate what needs to be done,” said Matthew Cosby, project manager of the Corps of Engineers. “We may do it in house and not contract it out, although we won’t do the actual construction.”

He said the Corps of Engineers is contracted by Congress to do construction and repairs of the Waterbury Bridge.

The Corps lowered the reservoir pool in 1981 and injected filler material in 1984 and reconstructed a portion of the toe of the dam and installed grouting in the gorge area to remediate seepage and settlement.

Vermont requested the Corps to conduct a dam safety assurance study to address conditions of the dam. The study was completed in 2000 and issued alternatives that included complete removal of the dam, constructing a new dam, reconstructing the gorge area or constructing a cutoff wall. The recommended plan called for constructing a filter shaft and monitoring structure in the gorge area to correct the seepage conditions. Construction was initiated in July 2002 and the installation of filters on the outlet conduit was completed in November 2002. Work in 2003 consisted of the initiation of construction of the secant cutoff wall and seepage control wells. Construction of the secant wall and dewatering system continued in 2004 through 2006. The Fiscal Year 2004 Appropriations Bill directed the Corps to design and construct a repair for the concrete spillway.

The spillway repair contract was awarded to Alltech Engineering in July 2005 at a cost of $693,000 and construction work was successfully completed in December 2005. The repairs were expected to extend the useful life of the spillway gates by 10 to 15 years. As part of this effort, a Design Report was prepared in 2006 for a full replacement of the spillway at a future date. The operation of the gates is restricted in part due to structural deficiencies and the flood storage pool cannot be raised to the full height as intended. The mitigation contract was awarded to Fleet Environmental in August 2005 at a price of $621,000 and work was completed in November 2006. Additional work to repair areas of the slope was performed on the mitigation site in fall 2007 and completed.

The state of Vermont allowed the reservoir to refill in September 2006. The reservoir reached normal pool at the end of October 2006 and overall construction of the seepage control measures was substantially completed in January 2007 with punch list items completed in fall 2007 and formally turned over to the state of Vermont. An 18-month performance and monitoring period followed the reservoir refill and demonstrated that the seepage control features continued to operate satisfactorily. The completed project, including the operation and maintenance of the project, was turned over to the state in September 2010.

Waterbury Dam is located on the Little River 3 mi. upstream from its junction with the Winooski River in Waterbury. The dam consists of a rolled earth embankment approximately 1,850 ft. long at its crest, 187 ft. high at its maximum section above the original river channel, and approximately 1,000 ft. wide at the maximum section. The spillway section is 261 ft. long and consists of two components. The first is a 161-ft. wide ungated concrete section with a crest elevation of 617.5 ft.

The second section is 100-ft. wide, contains three tainter gates, and has a sill elevation of 592 ft. The gates are 26.5-ft. high. Two of the gates are 20-ft. wide and were part of the original dam construction. The third is 35-ft. wide and was added in 1958 as part of a modification of the dam to satisfy updated hydrologic and hydraulic requirements.

“The Waterbury Dam and Waterbury Reservoir draw people from around Vermont and the country to appreciate our Green Mountain state,” said Leahy. “Tropical Storm Irene once again proved how crucial Waterbury Dam is to the safety and resilience of surrounding towns. I am glad the committee has supported my effort to once again provide the Army Corps of Engineers with the funds it needs to make much-needed repairs to this important piece …

Ben & Jerry’s Has an Actual Graveyard for Discontinued Flavors — and They’re Offering a Very Spooky Tour This Halloween

Ben & Jerry’s Has an Actual Graveyard for Discontinued Flavors  — and They're Offering a Very Spooky Tour This Halloween | Travel +  Leisure

Some people like to hang out in spooky graveyards around Halloween, and we’ve found the spookiest one of them. But this isn’t your typical cemetery. No, this is a graveyard of ice cream flavors. Cue the horrified gasps.

Ben & Jerry’s Flavor Graveyard, near the company’s plant and headquarters in Waterbury, Vermont, is where discontinued flavors go for their final rest. It’s also a neat tourist stop for ice cream lovers the world over. There, you can remember the flavors of days gone by like Wavy Gravy, Rainforest Crunch, Peanuts! Popcorn! or Ethan Almond. (RIP)

At the moment, the graveyard holds over 40 discontinued flavors that were either taken off the shelves to save space or were just mistakes against ice cream science. Did we really need popcorn-flavored ice cream? Each flavor in this sweet cemetery even has its own special epitaph for mourners to lament over.

“Ben & Jerry’s is known for outrageous, chunky, funky flavors,” said Flavor Guru Eric Fredette in a company press release. “But experimentation comes with risk, and not everybody likes our edgier ideas. Like everything else, ice cream flavors have a beginning and an end.”

This year, visitors who take a Ben & Jerry’s factory tour, along with a visit to the Flavor Graveyard, between Oct. 29 and 31 will be treated to a sample of a limited edition pumpkin pie ice cream available only in Waterbury. Everything’s better with ice cream, after all, even a stroll through a spooky “graveyard.”

More information on the Flavor Graveyard and Halloween tour can be found on the Ben & Jerry’s website. If you can’t make it to Vermont to pay your respect, a virtual tour is the next best thing.…

Waterbury Reservoir’s future could be at risk

The Waterbury Reservoir’s many swimming and boating possibilities drew 42,000 people this summer to the state park. Photo by Gordon Miller/Stowe Reporter

This article is by Miranda Orso, of the Stowe Reporter, in which it was first published Sept. 18, 2014.

There’s a real possibility that the 850-acre Waterbury Reservoir could simply go away.

An argument about how to run the flood-control dam that creates the reservoir could lead to a decision to stop filling up the reservoir for summertime use.

And the reservoir gets a ton of summertime use. It is the centerpiece of Waterbury Center State Park, which is wrapping up a record-breaking season. This summer, more than 42,000 visitors have enjoyed swimming, boating, picnicking, and hiking through the park, not to mention the naturalist programs that the park enables.

The reservoir’s future revolves around a new license for Green Mountain Power’s hydropower plant at the base of the flood-control dam. The utility has operated the hydro plant since 1953, but its license lapsed nearly two decades ago. Now, the company is seeking a new license from the Federal Energy Regulatory Commission.

In addition, a permit is required from the watershed management division within the state’s Department of Environmental Conservation.

Permit questions like these involve a balancing of hydropower benefits and environmental concerns.

The state agency will look at “everything from the effects on habitats, overall water quality, water temperatures, sediment levels as well as how the water flows and what happens to water downstream,” said Jeff Crocker, a river ecologist with the watershed division.

Those concerns also involve the effects on fish and other wildlife from raising and lowering the reservoir’s level season by season.

Now, the reservoir is drawn down to 562 feet above sea level in the winter, making room for the spring runoff that, except for the Waterbury dam, could cause flooding. The drawdown shrinks the surface area of the reservoir by 40 percent.

This is what the Waterbury Reservoir looked like for seven years after it was drained in 2000 for dam construction work. The 850-acre summer swimming and boating center all but vanished. Photo by Gordon Miller/Stowe Reporter

Once the runoff ends, the reservoir level is increased to 589 feet above sea level, creating the swimming-boating mecca at the state park.

The watershed division is concerned that the lowering and raising of water levels do not meet current water standards, said Bill Shepeluk, Waterbury’s municipal manager.

If the decision is to keep water levels low, then recreation at the reservoir would come to an end.

Shepeluk suspects state and federal officials have no idea of the furor that the reservoir debate will cause.

“This is a big issue to Waterbury residents, and people will be surprised at how passionate everyone feels about these things,” he predicted.

The community will have a chance to weigh in on the situation at a meeting tentatively scheduled for Oct. 7 from 6:30 to 8:30 p.m. at Thatcher Brook Primary School.

Competing interests

The Waterbury dam was finished in 1938 to prevent the kind of flooding that devastated Waterbury and other Vermont communities in 1927.

The dam holds back the water from the Little River, which flows south from Stowe toward the Winooski River. The Little River carries the runoff from the Stowe valley, including massive winter snowmelt from Mount Mansfield and the western side of the Worcester mountain range.

Once the reservoir was created, fish, loons and other flora and fauna made it their home.

Waterbury has already had a seven-year taste of what life would be like without the reservoir. In 2000, the reservoir was drained so construction workers could shore up the dam; the job took seven years and $24 million.

Shepeluk said Green Mountain Power tends to keep the summertime water level as close to 589 feet above sea level as possible, with a 1-foot leeway up or down. It uses that 2-foot range to generate electricity.

“These 2 feet of fluctuations don’t cause tremendous problems, but they can have a significant effect on water quality,” Shepeluk said.

The watershed division would prefer a permit that says the reservoir depth can’t flucuate up and down, Shepeluk said. Ultimately, it would like the water level to remain low, close to the normal wintertime level, he said.

If the water level is low, Green Mountain Power can still produce electricity from the Little River’s flow. But the hydropower would be less reliable. Now, adjusting the reservoir height ensures a steady flow of water through Green Mountain Power’s turbine, but a shrunken reservoir would make the hydropower dependent on the weather — similar to the utility’s other river-run facilities across the state.

Another option is to keep the reservoir even lower, near 550 feet above sea level — a 39-foot reduction in the normal summertime depth.

In this balancing of competing interests, Shepeluk said the hydropower plant, the environment and recreation could all be losers.

“We will be looking at solutions to allow all the stakeholders to get what they want,” he said.

While Crocker wouldn’t comment in detail, he said “there’s a possibility of changes to the recreation proportions of things but the opportunity would still exist. The parks may have to be redesigned.”…

Waterbury Reservoir seems pristine, but look closely

Like Lake Champlain, the Waterbury Reservoir is beloved, and fiercely protected by people like me — and you.

advertisement

We also know the reservoir’s health is at risk from the thousands of annual boaters, paddlers, anglers, and campers who do not always practice leave-no-trace, by the water-quality impacts of upriver agricultural and development runoff, by the introduction of aquatic and terrestrial invasive species, and by the conflicting priorities of a growing number of stakeholders.

At dawn a couple of Friday mornings ago, I launched my solo canoe onto the northern tip of the reservoir with my favorite paddling companion — a giant 6-year-old black Labrador retriever named Gabe. Gabe sleeps in the canoe, snoring loudly as his head rests on the gunwales.

At dawn, the Waterbury Reservoir is simply enchanting. In this magical moment around 6 a.m., the lifting fog races from south to north. A bluebird sky gradually emerges through a hole in the cloud. Sun rays stream urgently toward earth, and then suddenly disappear with the dissolving fog. The water sparkles with diamonds as the surface warms.

I watch for the bald eagles that nest nearby or the magnificent osprey. A fish jumps. A waterbug flitters. Canada geese and mallards fly overhead.

The lake is cool and smooth, disturbed only by the soft wake of my canoe. Water drips rhythmically from my paddle as Gabe and I slowly make our way to our favorite swimming and tennis-ball-chasing spot. A trout is startled by the shadow of my paddle overhead.

At dawn, the reservoir seems silent and pristine, until one listens and observes with intention.

advertisement

An angler and a sleepy young boy cast their lines from the shore, not really caring whether they catch anything. That’s not really the point, after all. But to get to this spot, they’ve cut their way through a dense mat of 7-foot-tall Japanese knotweed, tossing the stems into the moving river.

A great blue heron — an indicator species for the health of a lake — casts her bright golden eyes on me suspiciously. It seems to me improbable that such a large bird could be held firmly upon those slender legs.

She is standing in a patch of an invasive brittle naiad and I tell her I am sorry for that, but I know that our new boat access greeter is educating people about preventing the spread of invasive species into her lake.

A nervous beaver lures me from her pups and slaps the water surface, and slips into a den that this spring was adorned with a fading yellow laundry detergent bottle and a truck tire. The bottle and the tire are gone now, thanks to Green Up Day volunteers. I am proud of the two-year trash data study we conducted with support from Rozalia Project for a Clean Ocean and the resulting stewardship in the reservoir community.

In the mud along the river shore, there are tracks of a bear, a deer, a variety of birds, dogs of course, and from the angler and his son’s rubber boots too close to the eroding river shoreline.

At the end of our journey, Gabe and I return to the canoe launch and slosh through the smelly, silty water, carefully step around the deep gully that flows from the busy gravel parking area directly into the river. I am proud, though, that this ecological mess will be addressed this summer with state-of-the-art, low-impact, green technology and community outreach.

Our little nonprofit is making progress on our reservoir, thanks to effective partnerships and relationships.

The lake may be our teacher. It can tell us what it needs, but only when we listen.

We know that we can address the lake’s needs only when we research, understand, experiment; when we communicate, collaborate, and change our course when necessary — as do paddlers in a tandem kayak, or a Lake Champlain dragon boat.…